ROAD ENGINEERING
| Project Title |
: |
Bakun Hydro-Electric Project Access Road, Sarawak |
|
| Client |
: |
MCHJV |
| Services provided |
: |
Detailed Design |
| Project Description |
: |
Project involves 9 km of permanent access road from the existing JKR road to the power house, power intake, dam crest and boat landing area. The road is located in mountainous terrain transformers. The design alignment of the permanent access road was carried out with objective of minimising high cut and high fills slope areas. The investigation include geological mapping. The site which contain greywacke sandstone underlain with weak mudstone/shale. The design involved soil nail to strengthen the slope and guniting for erosion protection. |
| Project Title |
: |
Check Dam Project Access Road |
|
| Client |
: |
Lembaga Air Perak |
| Services provided |
: |
Design & Construction Supervision |
| Project Description |
: |
4.5km of access road in hilly terrain to the check dams at Ulu Kinta, Ipoh |
| Project Title |
: |
Storm water Management and Road Tunnel Project – Design, Review & Safety Audit |
|
| Client |
: |
Gamuda MMCJV |
| Services provided |
: |
Design Review & Road Safety Audit |
| Project Description |
: |
A double deck motorway 3km long in the by-pass tunnel (SMART) with ingress and egress links |
| Project Title |
: |
Realignment of Gap – Kuala Kubu Baru Road , Sg Selangor Water Supply Phase 3 (SSP3) – Design, Review & Safety Audit |
|
| Client |
: |
Gamuda Bhd. |
| Services provided |
: |
Design Review and Construction Monitoring and Road Safety Audit |
| Project Description |
: |
Realignment of the Kuala Kubu Baru - Fraser's Hill road (approx. 7.5km) affected by the Sg. Selangor dam project. |
|
|